HomePrint
EmailContactWeather

Go To Search
Click to Home

Streets Updates

   Total for Street projects $31.7M 

  Last updated: 2/06/2015 


 

Sidewalk Repair Program . . $3.0M

 

City Engineering working with Administration and Council to identify, design, and then contract for repairs

 

Murphy Street Viaduct . . . . .$2.2M

 

Construction for this project is being funded by the LA. DOTD.  2.1 million dollars will be re-purposed to other street improvement projects.

 

Knight Street . . . . . . . . . . . .$3.5M

Project is is completing design. Servitude acquisition will begin first quarter of 2015.  Construction is fully funded with the scheduled bid date to be the third quarter of 2015.

 

Traffic Signal System .  .  . . .$2.0M


Phase 1 Kings Hwy 95% complete.  Construction of Phase 1 is scheduled for third quarter 2015.  



City-wide Street Improvement Program…………………………….$21.0M


Hersey D. Wilson


Project is currently under construction. Project is scheduled to be completed by third quarter of 2015.

 

Miriam Street


Project has been completed.


  West Wilderness Way Project has been completed.


 

University Drive @ 70th

Project is under design.  Project is expected to be bid 2nd quarter of 2015.

 

 

Fairfield Avenue


Project design is completed.  Project is expected to be bid late 2nd quarter of 2015
.

 

Lewis Place/Carver


Project has been completed.


 

Brealock Drive

Design of Project is complete.  Project is scheduled to be bid 2nd quarter of 2015.


 

Woodmont Avenue

Project has been completed.


 

Walker Road

Project has been completed.


 

Kingston Road

Project design is complete. Project is scheduled for bids 3rd quarter of 2015.

 

Mackey Lane



Project has been completed.


 

South Kirkwood

Project design is completing. Project is scheduled for bidding late 3rd quarter of 2015.


 

Stoner Avenue



Project has been completed.


 

C.E. Galloway

Project is completing design. Project is scheduled for bids late 3rd quarter of 2015.


 

Oakdale

Design of project is underway.  Project is scheduled for bidding 3rd quarter of 2015.


 

Elvis Presley Blvd Median



Project has been completed.



 

Rosary Lane Sidewalk



Project has been completed.


 

Zeke Street



Project to go through A/E Selection.  This project is for design only.


 

Greenway Street

Project to go through A/E Selection.  Design is scheduled for 2nd quarter with construction to be scheduled 1st quarter 2016.


 

Midway Avenue

Project has been completed.


 

Missouri Avenue

Project is under design.  Project is scheduled for bidding 3rd quarter 2015.



 

Jewella Avenue (2 Phases)

Project has been completed.


 

Lakeshore Drive

Project has been completed.


 

Woolworth Road

Project design is complete.  To schedule bidding 1st quarter of 2015.



 

Scenic @ Tierra

Project has been completed.


 

Holcomb Street

Project has been completed.


 

Ackard Street

Project is under design.  Project is scheduled for bidding late 2nd quarter of 2015.


 

Carroll Street

Project has been completed.



  Captain Shreve Drive Project is under design.  Project is scheduled for bids 3rd quarter of 2015.


 

Huntington Lane

Design is complete.  Construction to begin following second bond sale or as funds become available.


 

Grover Place

Project has been completed.



 

Ashborne

Project is under design.  Construction to begin following second bond sale.




 

Village Green



Project is under design.  Project is scheduled for bidding 3rd quarter of 2014.






Last updated: 2/06/2015 


 


City of Shreveport, Louisiana